In an effort to improve connectivity and expand the recreational trail network for City residents, three significant trail projects are currently underway. The first of these projects, known as the Great Miami River Recreational Trail – Phase 2, is a 1.6 mile segment along the Hamilton Hydraulic Canal between Riverside Park and Canal Road. The second project is the Interceptor Trail that is being built along the river from Columbia Bridge (Pershing Avenue) to Riverside Park. A ramp will provide access from RiversEdge Park to the Interceptor Trail is currently being designed.
More detailed descriptions of each of these projects can be found below.
Great Miami River Recreational Trail – Phase 2
The Phase 2 project consists of 1.6 miles of paved recreational trail following the alignment of an existing gravel road used to maintain the hydraulic canal. It extends through portions of Hamilton, Fairfield Township, and St. Clair Township. The project begins at Riverside Park near Third Street in Hamilton and ends at the trailhead parking lot on Canal Road, near Allison Avenue.
A section of Phase 2 trail along the Hydraulic Canal
The project will utilize an existing bridge to cross the Hydraulic Canal at the trailhead parking lot on Canal Road, near Allison Avenue in Fairfield Township. A new bridge will be built near the Hydraulic Canal its confluence across with the Great Miami River. The trail will pass beneath existing CSX Railroad and US 127 (Third Street) Bridges over the Hydraulic Canal.
Phase 2 will fill the gap between the Phase 1 trail, at Canal Road, and the trail system along the river in downtown Hamilton. This will provide a non-motorized connection extending from Waterworks Park in Fairfield, along the river through downtown Hamilton, to Rentschler Forest MetroPark in Fairfield Township.
- Construction Cost
$2,231,244.00 of which $500,000 is being funded by a grant from ODNR, Clean Ohio Trails Fund; the balance of the project is being funded by the Hamilton Community Foundation.
- Contractor
Sunesis Construction Co.
2610 Crescentville Road
West Chester, OH 45069
- Schedule
Construction Start Date: October 23, 2014
Status as of December 10: 10% complete
Completion Date: April 17, 2015 (weather dependent)
Interceptor Trail
1.3 miles of paved trail is being constructed along the river from Columbia Bridge northerly to Riverside Park along with the sanitary sewer interceptor project. The sanitary sewer interceptor will convey sanitary sewer flows from the west side of the Great Miami River to the Water Reclamation Facility.
This project is mandated by a Consent Decree from the OEPA to mitigate Sanitary Sewer Overflows (SSO’s) in the City of Hamilton’s sewer system.
A portion of this project includes the construction of an asphalt road that is approximately 7,000 feet by 10 feet wide; this road will provide access to the sanitary sewer pipes and double as a recreational trail, connecting the Phase 2 project at the Hydraulic Canal near the Power Plant to the existing trail just north of the Columbia Bridge on the east bank of the Great Miami River.
- Construction Cost
$15,019,309.00 of which $308,000.00 is budgeted for the Access road/Bike path construction.
- Contractor
SJ Louis Construction, Inc.
13515 Broadway Street West
Rockville, MN 56369-0459
- Schedule
Construction Start Date: April 5, 2013
Completion Date: April 15, 2015 (weather dependent)
RiversEdge Bike Ramp
The ramp will connect the trails surrounding RiversEdge to the Interceptor Trail located along the toe of the levee. It will be located near the amphitheater and will extend to the south for 300-ft across the concrete revetment to the trail below. Construction drawings are being completed by the engineering consultant.
- Construction Cost
To Be Determined
- Contractor
To Be Determined
- Schedule
Construction Start Date: Spring 2015
Status as of December 10: Design 95% complete